Works on the future underground car park at the Albergue África site, on Calle Salvador Rueda, during the technical visit published by the council on 6 November. Excavation of the plot has reached 58.9 percent.
Works on the future underground car park at the Albergue África site, on Calle Salvador Rueda, during the technical visit published by the council on 6 November. Excavation of the plot has reached 58.9 percent. © Ayuntamiento de Marbella

Excavation at the Albergue África car park site reaches 58.9 percent, with total works at 15 percent

The future underground car park in Miraflores, with 571 spaces on two floors and sports facilities on the surface, has removed 33,000 of the planned 56,000 cubic metres, with the 480 micropile perimeter screen complete and the crowning beam under way.

Translated from the Spanish original. Leer en español

Excavation for the future underground car park at the Albergue África site, on Calle Salvador Rueda, has passed the halfway mark of the planned volume. According to the council note of 6 November, the dig has reached 58.9 percent of the plot, with close to 33,000 cubic metres of earth removed out of the 56,000 set out in the project.

The excavation is advancing alongside the other work fronts open on the site. The works as a whole stand at 15 percent execution, both against the planned timetable and against the budget amount, according to the assessment given by the councillor for the area, Diego López, in the same council communication.

The signing of the land cession agreement for the Albergue África plot, in February 2026, with the mayor of Marbella and the Junta de Andalucía's regional ministers for economy and finance and for social inclusion and youth.
The signing of the land cession agreement for the Albergue África plot, in February 2026, with the mayor of Marbella and the Junta de Andalucía's regional ministers for economy and finance and for social inclusion and youth. © Ayuntamiento de Marbella

The works are keeping a good pace and the project as a whole stands at 15 percent execution, both in relation to the planned timetable and to the economic amount of the budget

Diego López, councillor for the area

Screen complete and first anchoring line next

Homes on Calle Arturo Rubinstein, in Marbella. The councillor for the area links the new car park to the need for spaces in residential districts such as Miraflores.
Homes on Calle Arturo Rubinstein, in Marbella. The councillor for the area links the new car park to the need for spaces in residential districts such as Miraflores. © Zarateman, CC0, vía Wikimedia Commons

The perimeter retaining screen is finished: 480 micropiles now surround the works site. Crews are now working on the steel reinforcement and concreting of the crowning beam above that screen, after which the first line of anchors holding the structure will be installed. The excavation proceeds in steps, creating platforms from which the anchoring machinery operates.

571 spaces and sport on the surface

The finished facility will hold 571 parking spaces across two floors, with independent accesses from Calle Salvador Rueda, adapted spaces and charging points for electric vehicles, plus pedestrian stairs and lifts. López links the project to parking demand around Miraflores and to the sports provision that comes with it.

The project will answer the need for parking around Miraflores and will offer residents new sports facilities and meeting spaces

Diego López, councillor for the area

On the surface, the project sets aside the space for two artificial turf five a side football pitches of 50 by 30 metres and a multisport court prepared for basketball, indoor football, handball, volleyball, tennis and badminton. The programme is completed by four team changing rooms and two for referees, a first aid room, a store, accessible routes, spectator stands and gardens with native vegetation, trees, pergolas, a meadow area and a paved space intended for marquees and picnic tables.

Land ceded by the Junta

The works rise on the Albergue África plot, whose land the Junta de Andalucía ceded to the council free of charge. The cession agreement, covering 8,580 square metres, was signed in Seville in February 2026 by the mayor, Ángeles Muñoz, and the regional ministers Carolina España and Loles López, with a global investment then estimated at more than 24 million euros. That announcement spoke of around 600 spaces, a figure the project now under construction sets at 571.

In return, the council will provide 80 underground spaces to the Andalusian Youth Institute for users of the Inturjoven youth hostel, and the agreement also included a green area and a bus loading bay on Calle Trapiche. The draft municipal budget for 2027, presented on 5 November, reserves 7.4 million euros for this public car park and its sports facilities.